V. DRILLING OPERATIONS
AND PROJECT MANAGEMENT
In the sub-Sections
below, we first provide additional operational details for the
phases of the project associated with rotary drilling and continuous
coring. This includes the "rig-related" activities associated
with downhole measurements of pore pressure, permeability and
stress through perforations, as described previously in this proposal.
We then discuss the plan for on-site technical personnel, summarize
the services requested from ICDP (to whom this proposal is also
being submitted) and outline our strategy for project management.
Rotary Drilling
|
|
Figure 20. Direction drilling program for the
Parkfield hole. (click for more information) |
A detailed drilling and operational plan has been prepared
for this project by Mr. Louis Capuano, President and co-founder
of ThermaSource, Inc., a geothermal engineering consulting company.
Mr. Capuano has almost 30 years of experience in both oil and
gas and geothermal drilling and serves on a number of drilling
advisory panels. In this Section, we summarize the plan he developed
through extensive discussions with Mark Zoback and Steve Hickman
utilizing a preliminary drilling plan developed by ICDP as a starting
point. The information provided in this Section and in Appendix
A is intended to provide the reader with more detailed information
about the drilling, coring and operational plans than is described
above. This information is excerpted from a highly detailed report
entitled "San Andreas Fault Zone Drilling Project: Drilling
Program and Cost Estimates" (henceforth termed Drilling Report),
that was prepared by Mr. Capuano. Copies of this comprehensive
report will be provided to NSF under separate cover. While Section VI provides summary budgets for operational
aspects of this project (as well as science), the detailed budget
breakdowns for the many individual aspects of the operations,
services, supplies, etc., associated with drilling are provided
in the Drilling Report.
Figure 20 shows a detail of the planned
trajectory for the rotary hole in both cross-sectional and plan
views. Together with the geologic and geophysical criteria summarized
in Section III, a number of practical
and engineering considerations were used in designing this directional
drilling plan:
- Entering the geophysically imaged fault zone (as defined
in Figure 9) at a true vertical depth
of about 3.0 km (labeled as Target 1).
- Passing out of the fault zone at a depth such that the hole
trajectory passes as close as possible to the microearthquakes,
incorporating the uncertainties in their exact locations (Target
2).
- Starting the hole at a surface position that avoids known
faults and landslides and is accessible.
- Drilling straight through the fault zone to make subsequent
continuous coring and workover operations as simple as possible.
- Having a deviation from vertical such that deployment of
logging tools and monitoring instrumentation is not difficult
but still "gets across" the fault zone as rapidly and
directly as possible.
- Utilizing reasonable build-angles from a drilling and engineering
perspective.
|
|
Figure 21. Drilling and casing program for the
proposed Parkfield hole. (click for more information) |
The hole sizes (drill bits) and casing diameters shown
in Figure 21 were similarly designed on
multiple criteria:
- To yield a hole of sufficient size at the bottom (8.5"
open hole with a 7" casing) to make coring, downhole measurements
and fault zone monitoring possible.
- To drill open-hole sections of reasonable length.
- To set casing at geologically reasonable depths.
- To allow sufficient annulus in each section for good cement
jobs.
- To allow for a contingency program to be used if necessary
(described in Appendix A) that will still accomplish the project's
scientific objectives.
A breakdown of the time required to drill this hole and conduct
rig-related downhole measurements (210 days total) is shown in
Figure 22 and described in a step-by-step
manner in Appendix A. In preparing this timeline, reasonable and
conservative assumptions were made about the rate of penetration.
As is also described in Appendix A, should drilling problems necessitate
use of the contingency plan, the resultant hole will be smaller
(6 1/8" open hole with a 5" casing). This will still
allow coring of the multilaterals, downhole measurements and monitoring
instruments to be used, albeit with somewhat less flexibility.
Interestingly, the total time required to drill the contingency
hole is also estimated to be about 210 days, which results in
negligible changes in the overall cost of the rotary drilling
phase of the project, as described in the Drilling Report.
Testing Through Perforations
|
|
Figure 22. Depth versus time curve for the Parkfield
hole. (click for more information) |
The procedures associated with the fluid sampling and
pore pressure, permeability and least principal stress (i.e.,
hydrofrac) measurements through perforations are somewhat complicated.
These measurements require the cemented casing to be perforated
at 10 different depths, packers to be used to isolate the test
zone from the rest of the hole, and all of the test intervals
to be re-cemented prior to the fault zone monitoring phase of
the experiment. To minimize the rig time and costs associated
with this part of the project, a number of experimental procedures
were investigated. The procedure decided upon is termed a "Squeeze
Retainer Procedure" and permits the tests to be conducted
in sequence (see Drilling Report). This procedure involves the
following steps, working from the deepest test interval upward:
- Perforate the test zone with a wireline casing gun.
- Run in with a composite packer on the drill string and set
it above the perforations.
- Conduct a drill stem test (DST) to estimate formation permeability
and pore pressure from pressure build-up; use a wireline sampler
inside the drill pipe to obtain fluid samples (26 hours).
- Conduct hydraulic fracturing test with multiple pumping cycles
to determine the least principal stress (6 hours).
- Pull drill pipe out of the packer; displace almost all of
the fluid out of the pipe with cement.
- Stab pipe back into packer and squeeze cement below packer
into perforations.
- Pull drill pipe out of packer and wait for cement to cure.
- Perforate next test zone with wireline casing gun.
As explained in Appendix A, there is a prescribed sequence
of operational steps to make this possible. It is estimated to
take approximately 61 hours to conduct each measurement; the next
test interval will then be perforated and the entire procedure
repeated. When these tests are complete, the composite packers
left in the hole and residual cement inside casing will be drilled
out to leave the borehole with all the perforations plugged. Pressure
testing will be done to assure that this is the case. Any leakage
from perforations will be re-cemented ("squeezed").
This entire downhole measurement program will take about 3 weeks
of rig time to complete and should yield a comprehensive suite
of fluid samples and pore pressure, permeability and least principal
stress measurements at varied depths and positions within and
adjacent to the fault zone. At the end of this sequence of measurements,
a single interval will be perforated in order to monitor fluid
pressure during the initial fault zone monitoring phase of the
experiment. The drill rig will then be demobilized.
Continuous Coring
|
|
Figure 23. Case history for multilateral, directionaly
drilled hole in Prudhoe Bay, Alaska. (click for more information) |
Once we know where coring will provide the most useful
information about the fault zone (from a combination of geological,
geophysical and seismic observations), the series of multilateral
core holes described above will be drilled. The specifications
cited in the "case history" described in Figure
23 (from an advertisement for one of the service companies
that do this kind of work) are, in fact, fairly similar to those
in this project. The depth at which the multilaterals (~4 km)
is similar and the diameter of the main borehole (7") is
the same. The length of the drilled sections (~500 m) is somewhat
longer than the lengths we wish to core (250m). As in our project,
a slotted liner (a porous, uncemented casing) was left in each
multilateral hole. The purpose for utilizing the case history
in Figure 23 is obviously not to endorse
a particular service company. Rather, we present Figure
23 to emphasize the fact that the technologies required to
carry out this phase of the proposed project are currently in
use by the petroleum industry.
As described in Appendix A, we propose to bring in a separate
rig for the coring phase of the project. The budget (Section
VI) is based on the assumption of bringing in a deep wireline
coring rig. If possible, we would like to use the DOSECC deep
coring system that is being used for the first time in the Long
Valley drilling project at the time this proposal is being written.
As the ultimate capabilities of this system are not known at this
time, we have not based the coring plan on using this system.
However, if it can be used for this project, we will want to do
so.
We estimate that it will take 53 days to obtain the desired core
(see time breakdown in Appendix A). The procedures for core handling
are described in the previous Section.
Our current plan is to leave each core hole open (with a slotted
liner in it) to enable pore pressure to be monitored at multiple
sites in the fault zone.
On-Site Technical
Personnel
The detailed drilling
plan and budget submitted under separate cover lists a number
of cost items associated with personnel. While budgets are presented
and discussed in Section VI, there are
several points to note here because of their overall affect on
operations. First, the budgets include all supervisory personnel
associated with drilling. Thus, in addition to the personnel provided
by the drilling contractor(s), there will be drilling personnel
on site 24 hours/day representing the project science team who
will be providing supervision of drilling operations, keeping
track of progress and expenditures and working with the scientific
project management team (see below) to assure that the goals of
the project are met, on time and on budget.
As this project requires extensive efforts related to real-time
sampling of cuttings and gases, the drilling budget calls for
an additional geologist to be provided by the mud logging contractor.
This means that there will be 2 people on site 24 hours/day to
assure that sampling and sampling equipment are functioning properly.
Special equipment, such as the gas collection/gas chromatograph/mass
spectrometer system being provided by PI Jörg Erzinger requires
special manpower and attention.
Finally, we have budgeted for 2 geologists/technicians to be on
site a total 135 days during the rotary drilling phase of the
project and the full 50 days associated with coring. These individuals
will be able to assist the science team with the innumerable on
site technical activities, including:
- Keeping track (for the science team) of the cuttings, fluids
and gases being sampled continuously.
- Preparation of samples and conducting x-ray diffractometry
on selected cuttings and core samples.
- Helping with handling of the 8 spot cores to be obtained
in the rotary-drilled hole.
- Assisting in maintaining the DIS (Digital Information System)-a
complete digital data base of all scientific and engineering
results from this hole, to be provided by ICDP.
- Assisting with the appreciable continuous core handling activities
during the final phase of the project and entering of this data
into the ICDP data base. This includes scanning core, describing
core and preparation of digital input for DIS.
Operations at Long Valley indicate that a 3 person staff is
needed on a 24 hour basis to keep up with continuing coring operations.
As a member from the PI team will be on site continuously, the
2 positions budgeted here will assure that adequate personnel
will be on site to handle incoming core. As described in the Drilling
Report, the drilling plan includes costs for trailers to provide
onsite office space and housing for both supervisory and on site
scientific personnel.
Services Requested
from ICDP
This proposal is
being submitted to the International Continental Drilling Program
as well as the National Science Foundation, the U.S. Geological
Survey and the U.S. Department of Energy. The ICDP can provide
invaluable assistance in a number of areas:
- Engineering - As mentioned above, engineering personnel of
the ICDP were very helpful in developing preliminary drilling
plans for this project. Additional help provided by ICDP engineers
as the project progresses would be very beneficial.
- Maintaining a Comprehensive Data Base and Archive - A great
deal of engineering and scientific data will be obtained from
a wide variety of sources over the life of this project. We plan
to utilize the ICDP software system for maintaining a comprehensive
data base, providing tools for manipulating and plotting data
and for disseminating the data to interested scientists.
- Real-Time Data Base - The DIS data base developed by the
ICDP for organizing real-time drilling and scientific data, maintaining
it in a data base and making software tools available for data
analysis will be of great help to this project. In addition,
we want to make use of the software systems ICDP has developed
for making information about the project available to the global
scientific community via the world wide web.
- Core - The experience obtained with core handling during
the KTB project and ICDP projects preceding this one (Hawaii,
Long Valley, etc.) will be very beneficial to this project. It
is our hope to take advantage of both available equipment and
personnel in the core handling operations in the proposed project.
- National and International Scientific Participation - If
the proposed project becomes a reality, it will be a source of
scientific opportunity for scientists from around the world.
Our hope is that the ICDP will provide a key link to global scientific
community in two regards. First, to let them know about the scientific
opportunities presented by this project. Second, to help provide
an interface with these scientists to allow them to participate
in the project to the degree possible.
As mentioned above, we have budgeted for onsite technical personnel
to interface with the ICDP data base systems. They will need training
and periodic supervision by ICDP personnel.
Project Management
The management team of this project consists of Mark
Zoback, Steve Hickman and Bill Ellsworth. Working together, these
three individuals have hosted numerous planning meetings and workshops,
represented this project at even more numerous national and international
scientific meetings and special symposia, and worked closely together
to develop this proposal. The responsibility for overall project
management and interfacing between the scientific and operational
personnel will be shared by Mark Zoback and Steve Hickman.
As representatives of the different science teams, these three
individuals will continue to coordinate the various groups of
scientists as follows:
- Downhole Measurements - Mark Zoback
- Measurements on Core, Cuttings and Fluids - Steve Hickman
- Geophysical Site Characterization - Bill Ellsworth
- Fault Zone Monitoring - Bill Ellsworth
Steps to be taken to assure optimal project management are
as follows:
- Establish a Scientific Advisory Board - The purpose of this
board is to provide independent advice to the project on an as-needed
basis. Participants will come from both within and outside the
project science team.
- Planning workshops - We will be convening project-wide, three-day-long
planning workshops in the San Francisco Bay area during the first,
third and fifth years of this project. Members of our science
team have been asked to budget travel and per diem to attend
these workshops.
- Annual sub-group meetings - We will also be holding annual
meetings of smaller groups of principal investigators to discuss
operational and scientific details associated with downhole measurements,
core and fluids studies, site characterization, fault zone monitoring,
etc. These meetings will be timed to coincide with the Fall AGU
meeting in San Francisco.
- Special sessions - Special sessions will be held at national
and international scientific meetings (AGU, GSA, SSA, IUGG, etc.)
as appropriate.
- NSF/USGS reviews - To be held at the discretion of NSF and
USGS. NSF requires a review after 3 years for all projects that
extend more than 3 years.
- Sampling committee - To develop protocols for handling and
distribution of core, fluid and gas samples.
As Zoback, Hickman and Ellsworth have been friends and colleagues
for ~20 years (and Zoback and Hickman have worked together on
many other drilling and downhole measurement projects over the
years), we feel that the shared management approach described
here will be successful.
Back
to Top | Back to Table of Contents
| Back to Section IV | Proceed
to Section VI